The reconstruction of the energy part of factory was performed during the period of 2004-2013 in the nickel processing factory „Commander Ernesto Che Guevara“ in Moa (Cuba) in the following scope:
Delivery of two new steam boilers K6, K7 with steam output of 150 t/h
Delivery of steam turbo generator 25 MWe TG3
Modernisation of TG1 and TG2 turbine generators with a capacity of 12.5 MWe, material supply (construction is awaiting).
Modernisation of the machine room and fuel system
Modernisation and expansion of chemical treatment of water
The ENERGO CONTROL Ltd. company participated in the project as the supplier of the control system in the following scope:
Verification of actual state
Preparation of design documentation – basic engineering
Preparation of the draft of construction – detailed engineering
Delivery of the field instruments in the scope according to technical specification
Delivery of the installation material in the scope according to technical specification
Provision, revival and implementation of emission measurements
Delivery of valves including servomotors
Delivery of technical equipment for DCS
Delivery of architectural equipment for the control room
Delivery of DCS control system, including operator’s workstations
Technical assistance during the installation of devices and supplied equipment